The Landfill Board met on July 1 to discuss the budget and upcoming progress on the new transfer station.

Engineers have been working on required surveys and estimate that they will be finished before the end of July. The report cited at the meeting stated that the geotechnical investigation has been completed and the Foundation Design has been implemented. The engineers still must complete the Low Hazard/Low Volume Permit Application and submit that the site has been nailed down, and then complete the Conditional Use Permit. They must also look into and potentially complete a minor amend...